At Girl Scouts of Greater Los Angeles, we know every girl has the potential to unleash the leader within -- we just need to give her the support, experiences, and spaces to make it happen.  Our capital projects help us continuously provide girls with unique and safe spaces to learn and lead. Below are some detailed updates related to GSGLA's current capital projects. 

tree3_32

Camp Lakota Updates*

April 2019 Update - Construction Begins!

- Groundbreaking with Illig Construction. There will be a new dining hall, six villages, 24 tent platforms, and six restroom buildings.
- Site demo and clearing is complete
- All county permits have been secured
- Illig moved onsite early April and started work on April 8, 2019
- Site grading is complete
- Underground electrical is in process and will complete in late May
- Other site utilities to be completed in phases with all completed by December 
- Dining Hall work grading and pad work is in process
     - Foundation work to start in early May
     - Framing and roofing to be installed by mid-October
     - Interior work to be completed by mid-February
     - Completion expected in March 2020
- Cabin Villages including Restrooms
     - Foundation work to start in late May
     - Framing and roofing for all to be completed in Mid October
     - Interior work to be completed by early February
     - Start up commissioning and clean up to be done January through March  
- Project completion including city inspections and approvals is April 2020

May 2019 Update

- Construction team is currently erecting bathroom buildings for villages within the camp. Camp Lakota will ultimately have four villages of cabins and two new campsites with new bathroom buildings.
- Workers also cleared the original road to camp, making an easier camp arrival experience on Burbank Road.
- By summer 2020, the rebuilt camp will feature a new dining hall, a high and low ropes course, an archery range, a swimming pool, nature trails, and an equestrian center.

June/July 2019 Update

- Site grading is complete
- Site underground plumbing and site electrical work is complete
- Other site utilities to be completed in phases with all completed by December
- Dining Hall work and pad work is in process
        - Foundations are complete and all in slab plumbing and electrical is in  process
        - First pour of the Dining Hall slab is set for July 18, 2019
        - Framing and roofing to be installed by mid-October
        - Interior work to be completed by mid-February 2020
        - Completion expected in March 2020
- Cabin Villages including restrooms is in process
        - Pads have been graded and foundation work is underway
        - Framing and roofing for all to be completed in mid-October
        - Interior work to be completed by early February
        - Start up commissioning and clean up to be done January through March
- Project completion including city inspections and approvals is April 2020

August 2019 Update
Aug_2019_Lakota_Update

- Dining Hall Foundation and Slab on Grade is complete
- All County Permits have been secured and all Deferred Permits have been issued by the County
- Illig Construction has awarded all subcontracts and all major materials have been submitted and are either approved or will be approved shortly
- Site Underground Plumbing and Site Electrical work is complete
- Gas, Fire Water and Domestic water will be complete in early September
- Storm Drain and Sewer main work will be completed in September
- All Site connection to be completed by December

Aug_2019_Camp_Lakota_Update

Dining Hall
- Masonry retaining walls are complete
- Foundations and all in slab plumbing and electrical are complete and Slab on Grade has been poured
- Structural steel has been set
- Kitchen Framing is at 90% and roofing has started and will complete by October
- Glum lams material is all onsite and installation has started
- In- wall rough-in is 90%
- All kitchen equipment has been ordered and is in fabrication
- Interior work is scheduled to be complete by mid – February
- Completion expected in March 2020

Aug_2019_Camp_Lakota_Property_Update

Cabin Villages
- 50% of the concrete pads for the cabins are installed and the remaining 50%
to be poured by the first week in September
- The SIPs Contractor prepared a full-size mockup of the SIPs Exterior Panels.
This was reviewed and approved by the Team and these are in fabrication
- Framing and Roofing to start in September and is to be completed in Mid October
- Interior work to be completed by early February
- Start Up Commissioning and Clean up to be done January through March

Cabin Restrooms
- All of the restroom pads are complete
- Framing and Roofing to start next week and to be completed in Mid October
- Interior work to be completed by early February
- Start Up Commissioning and Clean up to be done January through March

*All construction dates are subject to change